June 2016 – Armosolo Tower Update

beaconjuly2016

 

As of June:

Overall general construction accomplishment is at 75%

Major structural works now completed.

Ongoing works:
• Masonry works up to the roof deck
• Aluminum Glass window installation up to the 38th floor
• Ceiling works up to the 28th floor
• Painting Preparation works up to the 31st floor
• Tiles installation up to the 28th floor